What are the key stages of a conductor stringing project?
2025-08-08A typical tension stringing project follows a well-defined sequence:
-
Preparation: Site clearance, access road preparation, and establishing the layout for equipment and conductor drums.
-
Insulator and Block Installation: Installing insulator strings and conductor running-out blocks on all towers within the stringing section.
-
Pilot wire stringing: Pulling a small-diameter pilot wire through the running-out blocks.
-
Pulling Rope Installation: Using the pilot wire to pull the larger-diameter pulling rope.
-
conductor pulling: The pulling rope is attached to the conductor via a Swivel and running board, and the hydraulic puller-OHTLstringingequipment.com/Hydraulic-Conductor-Tensioners.html target='_blank'>Tensioner system pulls the conductor through the blocks.
-
Sagging: After the conductor is in place, it is tensioned to achieve the precise sag as per the design specifications.
-
Clamping and Accessories: The conductor is finally clamped to the insulators, and accessories like spacers, dampers, and vibration dampers are installed.
-
Final Inspection: A thorough final check of the entire line to ensure all components are properly installed and secured.