What is the typical process for testing and commissioning EHV cables after installation?
2025-08-14Answer: The testing and commissioning phase is a crucial step to ensure the long-term reliability of an EHV cable system. This process typically involves a series of rigorous tests:
-
Pre-Installation Checks: Verifying the cable's integrity before it is pulled, ensuring there is no damage from transportation or handling.
-
Insulation Resistance Test: Using a megger to check the insulation resistance of the cable.
-
Partial Discharge (PD) Test: This is a vital test for EHV cables. It detects any minute electrical discharges that could indicate a flaw in the insulation or jointing, which could lead to future failure.
-
High Voltage AC/DC Withstand Test: Applying a high voltage to the cable for a specified duration to prove its ability to withstand operational voltage without breakdown.