What are the factory acceptance (FAT) tests and on-site commissioning checks I must insist on?

2025-08-19

Answer: Insist on: dynamometer load tests at rated kN, hydraulic pressure and leak tests, CTCS functional test, remote-control radio range/failure mode checks, sheave diameter & groove validation, electrical/PLC/telemetry EMC checks, and signed test reports. Include witness FAT option and documented commissioning checklist with acceptance criteria.